Our roof truss is finally up today. This critical component of the house has caused some major delay to the rest of the plan. Initially we were not too keen to change the entire roof, our contractor did remove some of the worn out timber beams and original plan was to replace these beams only.
However, after giving it some thoughts, Daddy decided to change the entire roof and replace the supporting beams with metal ones which last longer and are termite-proof. The new roof will also be covered with clay tiles instead of concrete tiles which reduces the amount of heat into the house. So with this major change, we spent a great deal of effort looking for roof specialist, getting quotations, comparing materials, their installation proposal, etc..
This really set us back by a month on the project schedule but I think we feel better with a sturdy roof over our heads. Another consideration we forgot was the "resting" period for hardwood flooring. We were reminded over the weekend by one of the timber flooring installer that we must let the wood rest for 4 WEEKS after installation before sanding. OOPSSS!
I do not have much time let before the second one comes and it was our plan to move into the new place before delivery. Now it looks like we have to stay put at the current place, do all we can up till I pop and move during or after confinement.